# How long does it take to fit a kitchen?

[![](https://flatpackmate.ie/img/team/alex-320.webp)Alex](https://flatpackmate.ie/author/alex/)19 Nov 20264 min read

Table of contents

1.  [01How long does it take to fit a kitchen?](#how-long-does-it-take-to-fit-a-kitchen)
2.  [02What is the day-by-day order of a kitchen fit?](#what-is-the-day-by-day-order-of-a-kitchen-fit)
3.  [03What has to happen before the fitter arrives?](#what-has-to-happen-before-the-fitter-arrives)
4.  [04How much time do stone worktops add?](#how-much-time-do-stone-worktops-add)
5.  [05How long is a whole kitchen project, start to finish?](#how-long-is-a-whole-kitchen-project-start-to-finish)
6.  [06What slows a kitchen fit down?](#what-slows-a-kitchen-fit-down)

Talk to our team

Send a photo of the job on WhatsApp and you will get a straight answer.

[WhatsApp](https://wa.me/353867354035?text=Hi%2C%20I%20found%20you%20on%20flatpackmate.ie%20and%20I'd%20like%20a%20price%20for%20a%20job.)[01 230 8966](tel:+35312308966)

Related service: [Kitchen fitting](https://flatpackmate.ie/kitchen-fitters/), from €1,500

Quick answer

A standard kitchen takes about **3 to 7 days** on site. Aloco Kitchens puts the fitting alone at 3 to 5 days, and IKEA Ireland says most of its installations finish in **5 to 7 days**. Stone worktops add **7 to 10 working days** after templating, and a full project with trades runs 2 to 3 weeks.

Key takeaways

-   Aloco Kitchens: a standard installation takes **3 to 5 days** for the fitting alone, and **2 to 3 weeks** with tiling, electrics and plumbing.
-   IKEA Ireland: most kitchen installations are completed in **5 to 7 days**.
-   Bark Ireland: a small kitchen takes **3 to 5 days** on site and a mid-range kitchen around **5 to 7 days**.
-   Worktops Ireland: stone is fitted within **7 to 10 working days** of templating; fitting itself takes 3 to 5 hours.
-   Kitchenworktops.ie: **2 to 3 weeks** from order to fitted stone worktop.
-   Screwfix: fresh skim plaster takes **2 to 5 days** to dry, depending on temperature, humidity and ventilation.

3 to 5 days

fitting alone for a standard kitchen

Aloco Kitchens, 2026

5 to 7 days

most IKEA Ireland installations

IKEA Ireland

7 to 10 working days

from stone template to fitted worktop

Worktops Ireland

The time on site is the short part. Most of the calendar goes on planning, delivery lead times, other trades and, with stone, waiting for the worktop. Knowing the order lets you book everyone once and live without a kitchen for as few days as possible.

## How long does it take to fit a kitchen?

Short answer

About 3 to 7 days on site for a standard kitchen. Aloco Kitchens puts fitting alone at **3 to 5 days**, IKEA Ireland says most of its installations take **5 to 7 days**, and Bark puts a small kitchen at 3 to 5 days. Stone worktops, tiling and trades stretch the whole job to 2 to 3 weeks.

IKEA adds that the time can vary from a few days to a couple of weeks, because every kitchen is planned differently. Size matters, but so do tall housings, an island, the state of the walls, and how far everything has to be carried.

## What is the day-by-day order of a kitchen fit?

Short answer

Strip-out and service changes first, then base and wall units, then worktops, then plinths, cornice and panels, then the connections. One UK fitter on MyJobQuote breaks it down as a day to rip out, two days for units, two for worktops and one for light rail, cornice and plinths.

A typical kitchen fit with laminate or wood worktops

Day

Work

Who

Day 1

Strip out old kitchen, services capped or altered

Fitter, RGI, electrician, plumber

Days 2 to 3

Base units levelled, wall units hung, tall housings

Fitter

Days 4 to 5

Worktops cut, jointed, sink and hob cut-outs

Fitter

Day 6

Plinths, cornice, light rail, end panels, doors aligned

Fitter

After the fit

Gas, electrical and water connections, certificates

RGI, REC, plumber

Source: our sequence, built from MyJobQuote fitters’ answers (UK) and IKEA Ireland. The trades usually need less than a day each. Our [kitchen fitting](https://flatpackmate.ie/kitchen-fitters/) price includes stripping out the old kitchen and taking it away.

## What has to happen before the fitter arrives?

Short answer

The plan must be final, every box delivered and checked, the room cleared, and any plastering dry. IKEA asks customers to check all boxes and appliances on delivery and to finish patching, painting and floor work first. Screwfix puts skim plaster drying at **2 to 5 days**.

-   Plan agreed: IKEA’s free planning appointment runs 60 to 90 minutes in store or online, or two hours at home
-   First-fix plumbing and electrics in their new positions, if anything is moving
-   Plastering finished and dry before units go against it
-   Every box and appliance checked against the order
-   Appliances on site, so cut-outs can be checked against them
-   A temporary kitchen set up in another room

Our [fitting readiness check](https://flatpackmate.ie/tools/fitting-readiness-check/) runs through the same list.

## How much time do stone worktops add?

Short answer

About one to two weeks. Stone is templated once the base units are fixed. Worktops Ireland says templating takes about an hour, fabrication **5 to 7 working days**, and most Dublin jobs are fitted within 7 to 10 working days. Kitchenworktops.ie says 2 to 3 weeks from order to fitting.

The kitchen works without worktops in between, or on a temporary board. The sink and hob cannot be connected until the stone is down, so plan meals around that gap.

Worktop type and how it changes the timeline

Worktop

When it is fitted

Extra wait

Laminate

During the fit, by the fitter

None

Solid wood

During the fit, oiled first

Oil drying time

Quartz or granite

After templating, by the stone company

7 to 10 working days

Want a date for your kitchen?

Send the plan and photos and we will give you a fitting schedule.

[WhatsApp](https://wa.me/353867354035?text=Hi%2C%20I%20found%20you%20on%20flatpackmate.ie%20and%20I'd%20like%20a%20price%20for%20a%20job.)[01 230 8966](tel:+35312308966)

## How long is a whole kitchen project, start to finish?

Short answer

Weeks, not days. Bark puts a full project at four to eight weeks from design to completion: one to two weeks for design and quote, two to four for manufacturing, then one to two weeks installing. Aloco puts a full project with tiling, electrics and plumbing at 2 to 3 weeks on site.

Delivery lead times drive the start date. IKEA notes you may get several deliveries, because made-to-measure worktops have their own lead time. Book the fitter once you have a confirmed delivery date, not before.

## What slows a kitchen fit down?

Short answer

Missing parts, walls out of plumb, surprise pipework, and appliances that arrive late. Older houses take longest, because units need packing level and panels scribed to the wall. Apartments add time for carrying units and 3 m worktops up stairs or in a small lift.

-   A damaged or missing cabinet stops the run at that point
-   Hidden pipes or cables behind the old units need a trade to move them
-   Floors that fall away mean longer legs or packing on every base unit
-   An extractor or hob that is not on site means the cut-out waits

A fit that starts with everything on site and the trades booked rarely runs over. For prices to go with this timeline, see our guide to [kitchen fitting cost in Dublin](https://flatpackmate.ie/guide/kitchen-fitting-cost-dublin/), and for clearing the room first, [kitchen removal cost](https://flatpackmate.ie/guide/kitchen-removal-cost/).

Need a price for kitchen fitting?

Send the plan or a photo and we will price it.

[WhatsApp](https://wa.me/353867354035?text=Hi%2C%20I%20found%20you%20on%20flatpackmate.ie%20and%20I'd%20like%20a%20price%20for%20a%20job.)[01 230 8966](tel:+35312308966)

## Frequently asked questions

How many days will my kitchen be out of use?

Plan on about a week with laminate or wood worktops. With stone, the base units go in first and the stone follows 7 to 10 working days after templating, so you may run on a temporary board for a week or two. Set up a kettle, microwave and fridge in another room.

Can a kitchen be fitted in one day?

Not a full kitchen. Fitters answering on MyJobQuote put units alone at about a day for a small flat, but a complete kitchen with worktops, plinths and appliances runs to several days. A one-day job is usually a door swap or a worktop replacement, not a full fit.

Should the plasterer or the kitchen fitter go first?

The plasterer, and the plaster needs time to dry before units are fixed to it. Screwfix puts skim drying at 2 to 5 days depending on the room. First-fix electrics and plumbing go in before plastering, so chases are made good before the kitchen arrives.

Does taking out the old kitchen add time?

Yes, usually up to a day. A fitter answering on MyJobQuote allows a day to rip out and alter service supplies. IKEA's installer does removal on day one if you choose that service. Gas and electrics must be made safe by the registered trades first.

Why does a stone worktop take so long?

Stone is cut to a template taken from the fixed units. Worktops Ireland says templating takes about an hour and fabrication 5 to 7 working days, with fitting usually 3 to 5 hours on the day. The units must not move once the template is taken.

## Next steps

-   [Kitchen fitting cost in Dublin: what a fitter charges in 2026](https://flatpackmate.ie/guide/kitchen-fitting-cost-dublin/)
-   [Kitchen removal cost: what it costs to rip out an old kitchen](https://flatpackmate.ie/guide/kitchen-removal-cost/)
-   [Who can connect a hob in Ireland, and who connects the oven?](https://flatpackmate.ie/guide/who-connects-oven-and-hob/)

## How we checked these figures

We loaded every page listed below on 19 November 2026 and checked each time figure against the page. Irish sources (IKEA Ireland, Aloco Kitchens, Bark, Worktops Ireland, kitchenworktops.ie) are used for overall durations. The stage-by-stage split comes from UK fitters' answers on MyJobQuote and the plaster drying time from Screwfix, a UK retailer; both are labelled. The day-by-day plan is our own sequence built from those figures, not a promise for any particular kitchen.

## Where the numbers come from

1.  [Kitchen installation service](https://www.ikea.com/ie/en/customer-service/services/kitchen-installation/), IKEA Ireland, checked 19 November 2026
2.  [Kitchen planning service](https://www.ikea.com/ie/en/customer-service/services/kitchen-planning/), IKEA Ireland, checked 19 November 2026
3.  [New kitchen cost Ireland 2026](https://alocokitchens.ie/new-kitchen-costs/), Aloco Kitchens, 24 February 2026
4.  [How much do kitchen projects cost in Ireland?](https://www.bark.com/en/ie/home-improvement-hub/how-much-do-kitchen-projects-cost-in-ireland/), Bark, updated 2 November 2026
5.  [Worktop services Dublin](https://worktopsireland.ie/dublin), Worktops Ireland, checked 19 November 2026
6.  [Worktop installation](https://kitchenworktops.ie/kitchen-worktop-prices/worktop-installation/), kitchenworktops.ie, checked 19 November 2026
7.  [Installing a kitchen: how long should it take?](https://www.myjobquote.co.uk/questions/installing-a-kitchen), MyJobQuote (UK fitters' answers), answers from 2019 and 2020
8.  [How to skim a wall](https://www.screwfix.com/guides/building-doors/plastering/how-to-skim-a-wall), Screwfix, checked 19 November 2026

![Alex, furniture assembler and carpenter at Flat Pack Mate](https://flatpackmate.ie/img/team/alex-320.webp)

About Alex

Furniture assembler and carpenter, Flat Pack Mate

Alex is the fitter behind Flat Pack Mate. He has worked in furniture assembly and carpentry in Dublin for more than 15 years, fitting single bookcases to full fitted kitchens.

[Guides by Alex](https://flatpackmate.ie/author/alex/)